Scoil Chuimsitheach Chiaráin, Carraroe, Co. Galway
National Energy Efficiency Upgrade Pilot Programme 2020
About The Project Overview ..
Dominic O’Connor Ltd. delivered a complete energy efficiency upgrade project at Scoil Chuimsitheach Chiaráin under the National Energy Efficiency Upgrade Pilot Programme 2020.
The project involved coordinated architectural, mechanical and electrical retrofit works including roofing upgrades, glazing replacement, external render systems, heating system upgrades, LED lighting replacement and photovoltaic installation.
The works were carefully phased within a live operational school environment to ensure uninterrupted teaching activities. DOCL acted as Main Contractor and PSCS, coordinating all specialist trades while delivering the project safely, on programme and to a high standard of workmanship.
Project Information
Year :
2023, 2024
Client :
Aramark Workplace Solutions – Energy Services
Final Account :
€1.58m
Programme :
5 Months
Category :
Services :
Main Contractor, Mechanical, Electrical, Retrofit, PSCS